APDRP
WORKS OF CONSTRUCTION & AUGMENTATION OF 33/11 KV S/s DURING 2006-07
- Construction of 14 Sub-stations of 33/11 KV (94 MVA & 243 Km. Line) under State Sector/Deposit Scheme.
- 30 Sub-stations of 33/11 KV (198 MVA & 331 Km. Line) will be constructed from Internal Sources with augmentation of 37 existing 33/11 KV Sub-station with increasing capacity of 117.5 MVA.
- Under Special Component Plan (SCP), construction of 33/11 KV Sub-stations with 2x5 MVA & 9 Km. Line at Bhagwanpur in District Haridwar and 1x3 MVA & 15 Km. 33 KV Line at Harsil in District Uttarkashi is proposed. In this scheme augmentation of existing 33/11 KV Sub-stations at Dharchula in District Pithoragarh, Sult & Syaldey in District Almora and Kundeswari & Dineshpur in District U.S. Nagar with increasing capacity of 13 MVA.
- Under Tribal Sub Plan (TSP) installation of additional DTRs, Aerial Bunch Conductor (ABC) and Conversion of single phase to three phase is proposed.
| S.No |
Description |
Downloads |
| 1 |
Activity Wise Progress of APDRP works As on 31-Oct-2008 |
 |
| 2 |
APDRP FUND UTILISATION As on 31-Oct-2008 |
 |
| 3 |
Status of Financial Progress of APDRP Works As on 31-Oct-2008 |
 |
|